Big Systems That Work Started as Small Systems That Worked


A person placing a block into a pile of wooden blocks

One in six. That is the share of IT projects that blew through their budgets by an average of 200%, with schedules running almost 70% late, when Bent Flyvbjerg and Alexander Budzier studied 1,471 projects for Harvard Business Review in 2011. The average overrun was a fairly boring 27%. The danger lived in the tail, and the tail was full of big, ambitious systems designed all at once.

A pediatrician named John Gall saw the pattern decades before that data existed. In his 1975 book Systemantics, he wrote the line that now carries his name:

“A complex system that works is invariably found to have evolved from a simple system that works. A complex system designed from scratch never works and cannot be patched up to make it work. One has to start over, beginning with a working simple system.”

That is Gall’s Law. Software people quote it constantly. Managers almost never do, which is strange, because managers are the ones who sign off on the new intake process, the new scheduling model, the new tool that is going to replace five spreadsheets and two inboxes on the first of the month.

What the big launch actually looks like from the inside

HealthCare.gov opened on October 1, 2013. By the end of that first day, internal notes released by Congress showed six people had successfully enrolled. When the HHS Office of Inspector General later reviewed five years of documents, its conclusion was not mainly about code. It found the launch failed largely because of poor management and leadership that left project tasks unclear and decisions delayed.

In April 2018, the UK bank TSB moved its customer data onto a new platform. The data moved fine. The platform did not work. Branch, phone, online and mobile banking were all disrupted, a significant share of its 5.2 million customers were affected, and the bank did not return to business as usual until December. The regulators eventually fined TSB £48.65 million, describing the program as ambitious, complex and carrying a high level of operational risk.

Neither of those was a team of fools. Both were teams that tried to switch on a finished, complicated system and discovered, on launch day, the hundred interactions nobody had seen working together before.

Your version is smaller, and the shape is identical. A new ticket triage process gets designed in a conference room with every category, every escalation path and every SLA mapped out. It goes live on Monday for the whole department. By Wednesday, people are routing around it, and by the following month you are writing exceptions to the exceptions. That is Gall’s second sentence in action: you cannot patch a system into working when it never worked in the first place.

Why managers keep designing from scratch anyway

The big launch is attractive for reasons that have nothing to do with whether it works.

It looks decisive. A phased rollout reads like hedging in a steering committee, and a single go-live date fits nicely on a slide.

It spends the budget once. Funding often arrives as a project with a start and an end, which quietly rewards building the whole thing and punishes building a small piece, learning, and asking for more.

It lets you design for the problems you can imagine. The trouble is that a working system mostly handles problems nobody imagined, and those only show up when real work flows through it.

Running operations at a large telecom, I watched a replacement for an alarm correlation tool get scoped as a full cutover: every network element, every rule, every on-call notification, one weekend. We pushed back and got permission to run it in parallel for a single region first. The first week turned up a duplicate-paging loop that would have woken the entire on-call roster several times a night if we had gone national. Fixing it took two days. Finding it at full scale would have cost us the trust of every technician who had to answer those pages.

Starting small without starting timid

Gall’s Law is not an argument for small ambitions. It is an argument about the order in which you build.

Find the smallest version that does real work. Not a demo, not a pilot with fake data. One team, one queue, one shift, doing actual work under the new process. In fractional COO engagements, when an owner asks for a full ERP, the first move is usually one shared intake sheet that every order passes through. If people will not use the sheet, they will not use the ERP either, and you just saved a six-figure lesson.

Make it work before you make it bigger. “Work” means the people using it would object if you took it away. Until then, adding features adds failure points to something that has not proven it can carry load.

Grow it one connection at a time. Each new team, integration or rule is a change you can still reverse. That matters, because most decisions are more reversible than managers treat them, and a staged rollout keeps them that way.

When it truly is broken, go back to the last version that worked. This is the hardest part of Gall’s advice to follow, because of the sunk cost. Rolling back to the simple system feels like losing months. Patching a system that never worked usually costs more.

One caution runs the other way. Before you tear out a messy old process to replace it with a clean simple one, remember that the old process probably evolved too, and some of its strange steps are fences somebody put up for a reason. Gall’s Law respects evolved systems. It just insists you evolve the new one as well.

The next time someone hands you a beautiful diagram of the complete future state, ask a single question: what is the smallest part of this we could run for real next week?

Ty Sutherland

Ty Sutherland is an operations and technology leader with 20+ years of experience. He is Director of IT Operations at SaskTel, founder of Ops Harmony (fractional COO and EOS Integrator), and former COO at WTFast. He writes Management Skills Daily to share practical management frameworks that work in the real world.